Custom glazing systems development schedules: When project timelines drive design choices

Harbor Point Custom Glazing Systems
Design and Engineering

Custom glazing systems development schedules: When project timelines drive design choices

The development of custom glazing systems requires adequate lead times to investigate the range of possible material and design options, as well as to accommodate testing, mock-ups and any other project requirements. At Bellwether, we find an average custom project timeline is between 18 and 22 weeks, considering: 8-10 weeks for design, samples, and approvals