The development of custom glazing systems requires adequate lead times to investigate the range of possible material and design options, as well as to accommodate testing, mock-ups and any other project requirements. At Bellwether, we find an average custom project timeline is between 18 and 22 weeks, considering: 8-10 weeks for design, samples, and approvals